Planning timeline
Submitted by Vikram Khatri on Fri, 2006-09-29 14:21.
|
Task Name |
Duration |
Start |
Finish |
| Complete list of Civil/Landscape Firms | 1 days | Wed 9/27/06 | Wed 9/27/06 |
| Send out RFP | 1 days | Thu 9/28/06 | Thu 9/28/06 |
| Recieve Proposals | 7 days | Fri 9/29/06 | Mon 10/9/06 |
| Evaluate Proposals | 4 days | Tue 10/10/06 | Fri 10/13/06 |
| Interview firms | 2 days | Mon 10/16/06 | Tue 10/17/06 |
| Award contract | 0 dayd | Tue 10/17/06 | Tue 10/17/06 |
| Site Design | 15 wks | Wed 10/18/06 | Tue 1/30/07 |
| Site Survey | 2 wks | Wed 9/27/06 | Tue 10/10/06 |
| Site Plan Approval | 6 mons | Wed 1/31/07 | Tue 7/17/07 |
| Groundbreaking - Janamasthmi 07 | 0 days | Tue 9/4/07 | Tue 9/04/07 |
| Design Building | 9 mons | Tue 9/27/07 | Tue 6/5/07 |
| Building Permit | 4 mon | Wed 6/6/07 | Tue 9/25/07 |
| Construction | 11 mon | Wed 9/26/07 | Tue 9/29/08 |
| Grand Opening Janamasthami 08 | 0 days | Sat 8/16/08 | Sat 8/16/08 |